Step 1: After receiving the job schedules, I first determine if the current period total contract revenue earned and cost of revenue earned on the job schedules agree with the same lines on the company’s income statement.
-
- Does the schedule reconcile?
- If not, why?
- Are there costs hitting the income statement that are not being charged to projects? Most of the time, the schedules don’t reconcile because indirect costs are not allocated to individual projects.
- Does the total over and under billings on the jobs in process schedule agree with the balance sheet?
- Does the schedule reconcile?
Starting my analysis with job schedules that reconcile to the balance sheet and income statement gives me comfort that I have a complete list of contracts, contract amounts, contract billings to date, and contract costs to date. The variable is the estimated cost to complete for each project. By performing steps 2-4 below, I am attempting to understand the company’s project performance and, ultimately, the accuracy of the revenue recognized.
Step 2: I identify contracts that are significant to the contractor’s operations by conducting a contract risk assessment. I look at risk factors such as type of contract, size of the contract, type of work performed, project percentage of completion, geographic location, large over or underbillings, and other factors that I consider relevant for each contract. Once I identify contracts that I deem are significant, I move on to step 3.
Step 3: This step is about analyzing and getting answers to questions. Some of the questions asked in step 3 are:
-
- How is the project's estimated cost at completion determined?
- Why is Project X so under/overbilled?
- Why is Project Y’s gross profit % so much different than the company’s historical gross profit?
- Why is Project W showing a loss? Has the contractor properly accounted for the entire loss as required by generally accepted accounting principles?
- Why is Project Q’s contract value so much larger than other projects that the Company normally performs?
- Why is the overall total gross profit percentage on the jobs in process schedule so different from the company’s historical gross profit percentage?
- Why is the company performing below or above expectations in a certain industry segment?
- Why is project manager Z performing above or below expectations on his projects?
Step 4: Perform a gain fade analysis on significant projects open as of the prior period end. At this step, I am looking to determine how the project finished versus what the company showed on the prior year's jobs in process schedule. I am looking for the following:
-
- Did the project perform as expected?
- Was there a large gain/fade on the project?
- If there was a large gain/fade on the project, what caused it?
- Does the contractor have a history of providing me with accurate project estimates?
- Do I need to include a change in the estimate footnote in the audited or reviewed financial statements because of a large project gain or fade?